Update: Feb 16

Today the Tape and Bed men continued, the tub and tub filler were delivered and your new cabinetry was installed.  The tile was delivered and tomorrow they will go to work on the hardi-board and filling the shower pan.  Templates for the counter tops will be made Wednesday.  I will also place the tub and tub filler.  I will send you a photo for your approval so if it is convenient to have you phone handy to review, that would be a big help so I can get the plumbers on the location of the drain and supply right away.

Thanks!